Saturday, January 20, 2007

Quick up to date Rundown

Okay first post and a quick rundown of the process up until now.

Back in October 2006 the slabs were poured on both units and left to cure for a few weeks.

26 October saw the commencement of the Frame stage and this was completed on 13 November for both blocks.

Bricking stage commenced on December 6 and completed by end of year. The roofing commenced on the 18 January and still being completed as of today.

In other matters, the water meters were stolen in the new year of January , week of 9.


Curently Tiles have been ordered, but this is a bit of drama because the tile company seems a bit dodgy and we'd like to get out tiles delivered a bit earlier to get our despost and tiles out before they do a runner. They are nice tiles however, 500 by 500 in a gloss marble, very nice.

Looking at carpets, seems like just under 2000 with underlay