Well literelly in a couple hours will make my way to the Big day Out 2007. Heres an update on the house progress. As we speak, the SA Plasterboard crew are on the site doing the gyprock. Roofing was complete last friday 27 and paid for. The insulation batts and gyprock was delivered this week on the days of 30 and 31. On the 1st the insulation was installed into all the external walls and then on Thursday 1 February the gyprock commenced, albeit slowly. Not even one room is complete at this stage and just the ceiling and a few walls. Also, the steel that we placed at the back of the block is gone now, so I suspect someone in the hood has helped themselves.
After gyprocking will be lockup and at that stage I can enquire about a handover date.